OK we have leveled and compacted the house interior floor AGAIN!
Now we are ready to prep the floor for the heating system.
|
|
Insulation is rolled out to insulate the warm concrete from the soil. |
|
Looking back into the kitchen. Each joint is taped. |
|
|
|
|
Our neighbor Ted helps us with this project also. Thanks Ted! |
|
|
|
|
|
6x6 wire mash is placed on top of the insulation. This wire will provide a place to tie down the heating pipes. |
|
|
|
|
|
Wire is almost done. |
|
Pipes are laid out and wired to the mesh. |
|
|
|
|
View from the kitchen - almost complete! |
|
|
|
|
|
Everything comes out in the utility room. Sure hope its all in the right place! |
|
|
|
|
|
The different zones are pressurized to insure that there are no leaks.
We did check them through the floor concrete process as well just to insure
nothing got poked. |
|
|
|
|