OK we have leveled and compacted the house interior floor AGAIN!
Now we are ready to prep the floor for the heating system.


Insulation is rolled out to insulate the warm concrete from the soil.
Looking back into the kitchen. Each joint is taped.

Our neighbor Ted helps us with this project also. Thanks Ted!

6x6 wire mash is placed on top of the insulation. This wire will provide a place to tie down the heating pipes.

Wire is almost done.
Pipes are laid out and wired to the mesh.

View from the kitchen - almost complete!

Everything comes out in the utility room. Sure hope its all in the right place!

The different zones are pressurized to insure that there are no leaks. We did check them through the floor concrete process as well just to insure nothing got poked.